Risk factors at planning phase (feasibility study on a proposed project & establishment of an execution plan of budget) |
P01 | Inadequate understanding of the recipient country’s needs & demands |
P02 | Inadequate survey on the prospective project site and improper suggestion on the site selection |
P03 | Unclearly divided undertakings between KOICA & recipient country |
P04 | A mistake in the project schedule estimation |
P05 | A mistake in the project cost estimation |
P06 | Inadequate survey on the local construction environment |
P07 | A mistake in the project size estimation not considering the project budget |
P08 | Improper space program establishment |
P09 | Improper design instruction |
P10 | Improper suggestion on the selection methods of designer, contractor, supervisor, and CM for the project implementation |