Table 13 Perception difference on the empirical risk factors

Var.code Level of frequency of occurrence Level of severity of effects on the project
Mean of responses from Mann Whitney U test Cronbach’s alpha Mean of responses from Mann Whitney U test Cronbach’s alpha
Owner (KOICA) CM Owner (KOICA) CM
P01 3.33 2.50 .064 .845 4.17 3.00 .006** .737
P02 3.00 2.20 .024* 4.17 3.50 .051
P06 3.61 2.60 .009** 3.89 3.20 .057
D07 3.39 3.00 .245 .848 4.17 3.40 .016* .841
D08 3.11 2.30 .035* 3.33 3.70 .226
B02 2.78 3.80 .031* .820 3.67 4.70 .004** .802
B05 3.44 2.50 .018* 4.06 3.30 .045*
B09 2.94 2.40 .265 3.50 2.70 .027*
Var.code
P01 Inadequate understanding of the recipient country’s needs & demands
P02 Inadequate survey on the prospective project site and improper suggestion on the site selection
P06 Inadequate survey on the local construction environment
D07 Improper cost estimates
D08 Unclearly specified undertakings & exclusion out of the contractor’s SOW
B02 Inappropriate method to select a preferred bidder
B05 An incorrect budget estimate published at a bid announcement
B09 An inappropriate clause of the priority of design documents (drawings, specification, BOQ)
p<.05,
p<.01 (two-tailed test).
Note: CM, Construction Manager.